Staffing Renewable Interconnection Projects

The panels are the easy part. The queue position, the study work and the point of interconnection are where the engineering headcount actually goes.

· 8 min read · Hiring Guides

Renewable developers consistently underestimate the electrical engineering load of interconnection relative to the generation plant itself. Queue studies, collector system design, substation and protection design, and utility coordination absorb the bulk of technical hours, and each is served by a smaller labour pool than the balance-of-plant work.

Map headcount to the interconnection milestones

  1. Queue and study phase - power systems engineers running load flow, short circuit and stability studies against the utility's model
  2. Design phase - collector, substation, protection and control engineers producing the issued-for-construction package
  3. Construction phase - field and QA/QC engineers managing installation and utility witness points
  4. Energisation - commissioning and relay test engineers executing the utility's witness test program

Power systems study engineers are the constraint

The engineers who can run and defend interconnection studies in the utility's own software are a small national pool serving developers, consultants and utilities simultaneously. Where the study workload is intermittent, contract or consultancy capacity is usually more realistic than a permanent hire, provided it is contracted before the study deadline rather than after a deficiency notice.

Interconnection staffing lead times
PhaseCore disciplinesStart search
StudyPower systems, protection3 to 4 months before submission
DesignSubstation design, collector, civilAt study completion
ConstructionField, QA/QC, project controls8 to 12 weeks before mobilisation
EnergisationCommissioning, relay test3 months before the utility witness date

Portfolio developers should plan across projects

Developers running several projects through the queue simultaneously get far better economics from a rolling workforce plan than from per-project requisitions, because the same study and commissioning specialists can be sequenced across sites instead of competing for the same scarce hires in parallel.

Summary

Key takeaways

  1. Interconnection, not generation plant, drives most of the engineering headcount on renewable projects
  2. Power systems study engineers are the scarcest discipline and usually best engaged on contract
  3. The utility witness date is fixed and should anchor the entire staffing plan
  4. Portfolio developers should staff across the pipeline rather than per project

Answers

Frequently asked questions

Question not covered here? Ask a recruiter directly - you will get a straight technical answer, not a callback from a salesperson.

Need this applied to your own requisition?

Our recruiters will run the same analysis against your scope and send back a written market view for the disciplines you are planning.